Skip to content
HN On Hacker News ↗

Why Texas Is Making Data Centers Wait

▲ 42 points • 90 comments • by gmays • 4w ago • HN discussion ↗

Pangram verdict · v3.3

We believe that this entire text is human-written.

12 %

AI likelihood · overall

Human
100% human-written 0% AI-generated
SEGMENTS · HUMAN 1 of 1
SEGMENTS · AI 0 of 1
WORD COUNT 1,703
PEAK AI % 12% · §1
Analyzed
Oct 11
backend: pangram/v3.3
Segments scanned
1 windows
avg 1703 words each
Distribution
100 / 0%
human / AI fraction
Verdict
Human
Pangram v3.3

Article text · 1,703 words · 1 segments analyzed

Human AI-generated
§1 Human · 12%

At the end of 2024, Texas’ grid operator had 63 GW of large new customers in its queue. By this June, that figure reached 474 GW, more than five times record peak demand, about 90% of it data centers. Then Texas hit pause. What began as directions for data centers to pay for their own grid upgrades has since escalated to a freeze on all new permits. If you care about AI and American reindustrialization, this is important to understand. Why did it do this? The upcoming election is part of it, but the underlying issues are worth digging into. The first is the interconnection queue. This pause is just as much about how projects apply for approval as it is about the projects themselves. Developers routinely spam projects across several sites, and many are speculative builds with no customer yet. Often these new developers have never even plugged in a GPU, let alone a power plant, so dealing with low-quality submissions puts ERCOT, which runs most of the state’s grid, in a tough spot. Planners can’t tell which are real, and they don’t want ratepayers paying for upgrades built for projects that never show up. The second issue is community alignment. Noise, water, emissions, and power bills are top of mind for anyone who lives nearby. And regardless of the reality of these issues, people deserve straight answers when a data center comes to town, and they haven’t always gotten them (as of June, only 28 of 377 companies had answered a state survey on their resource use). In Hood County, commissioners were asked to support a tax waiver for “Project Patriot” without knowing who it was. To be fair, code names are common while companies shop for sites since a famous buyer can drive up prices, but that logic becomes tougher to defend once officials vote on tax breaks. The broader political backdrop is important, but I’ll be focusing on the energy side: why it’s so hard to power a data center, all the ways developers are trying to do it anyway, and where things are likely headed. What connecting to the grid actually means How Amazon purchases power helps illustrate what’s changed. For the last decade, they’d find a utility with network capacity, sign up as a large load, then enter long-term contracts to match their use on paper. These were often purely financial, meaning you didn’t always have to prove the power could reach you, and the grid connection was easy because utilities had spare network capacity. That’s no longer true. The grid is stretched thin, and almost any new large load or generator now requires an upgrade. Power flows across every connected path, so buying from one plant doesn’t reserve a route to your building (there are even markets for transmission congestion rights). So buyers went after firm power (available around the clock) they could claim more directly, typically by restarting retired plants or by building next to existing ones. Neither was a true escape, and some of the loudest fights are over “colocation,” which ERCOT describes as drawing power from a neighboring plant before it reaches the grid: Susquehanna: Amazon bought a campus next to Talen’s nuclear plant, but FERC, the federal grid regulator, rejected Talen’s bid to send it more power directly. Utilities had argued it would let the campus dodge grid fees and push fixed transmission costs onto everyone else. After they restructured the deal, Amazon pays for delivery like any other customer. Freestone: CyrusOne’s 760 MW campus beside Constellation’s gas plant needed approval from the Public Utility Commission of Texas (PUCT), since it effectively takes much of the plant’s output from everyone else. The PUCT said yes in May, as long as the campus can cut its use or switch to backup power within 30 minutes of an ERCOT call. Armstrong County: Two Crusoe data centers beside a wind farm got the same rule, and the second, approved in July, must also shed its entire load, so together they’d cut nearly twice what the wind farm can produce. Interconnection studies are how grid planners identify the wires and substations that need upgrades for any addition to the network. ERCOT used to review studies individually under rules built for 40 to 50 large loads at a time, but 2025 brought 225 new requests by mid-November. So this June, the PUCT approved a new batch approach. Under “Batch Zero,” ERCOT studies large loads of 75 MW or more together and allocates grid capacity among them. Primarily, the studies ask what happens when something breaks. NERC’s standard, the baseline for reliability across North America, covers a broad set of outage scenarios, with ERCOT adding its own requirements. Planners might simulate a transformer outage, then knock out a line or generator on top of that. Maintaining that reliability standard without shedding more load often means building additional infrastructure. A newer risk is load dropping off the grid all at once. Many data centers switch to backup power at the first voltage dip to protect their hardware, so one bad fault can pull an enormous load off the grid in seconds. This happened earlier this year in Virginia, but was fortunately handled well. Texas has even less room for error since ERCOT’s grid is largely isolated. Under some conditions, ERCOT can lose only about 3.2 GW of load at once before causing issues. A new voltage ride-through rule now requires new data centers to stay connected through routine faults, and I’ve even heard of labs running dummy jobs after a training run fails just to keep load from dropping abruptly. All of this can sound overly conservative, but the system was designed to put reliability ahead of cost. Put simply, the grid is built for the hot summer days and frigid winters when failure can mean life or death. That duty is what makes sizing the grid so hard; you build for a few peak hours but pay for it all year. So who does pay for all this resilience? Texas typically splits transmission costs by each large customer’s demand during the grid’s summer peaks, so a big load that ramps down on the hottest afternoons can skip much of its share of the transmission bill. In July, regulators proposed counting all 12 monthly peaks instead and charging large loads as if they ran at full size. In other words, large buyers would pay in proportion to how big their electricity pipes need to be, not how much is flowing through them. Sounds simple enough, but splitting up costs is often the slowest part of interconnection. An upgrade built for one campus may also improve reliability for existing customers or make room for future growth that’s hard to value up front. And if any new development runs over budget or its load never shows up, everyone else is forced to cover whatever the developer’s commitments didn’t. And those commitments are surprisingly cheap to make. The PUCT’s new large-load rules, effective October 8, charge a flat $100,000 study fee plus a $50,000-per-MW deposit. The deposit weeds out some speculative projects, but it’s a thin filter. ERCOT can reassign a project’s capacity if it falls two years behind, but even a project that loses its capacity forfeits just 20% of the deposit (at least $10 million on a 1 GW campus), plus whatever the utility has already spent. Most importantly, the deposit typically only backs the upgrades built for that project, not the more expensive regional lines whose cost everyone on the grid shares. Fully connecting a large data center can take 5 to 10 years. To accelerate deployment, a phased connection approach is becoming more common, which gives the utility more gradual targets to plan around, as well as a way for the developer to prove they can handle everything they’ve asked for. All of this also assumes Batch Zero is moving, which it isn’t right now. ERCOT has even paused approvals for data centers of 75 MW or more to switch on, including 17 that had finished every other ERCOT step. Until the audit’s December report settles which projects are eligible, ERCOT can’t study them together, so the timeline is “TBD” and the load forecast is on hold. What bringing your own power solves For a developer facing the interconnection queue, skipping the grid entirely looks appealing. Idle GPUs cost far more than the electricity to run them, so speed matters most — what folks call “time to power.” That’s why developers are planning to bring their own power on site (“behind the meter”), but almost always alongside a connection to the grid, or as a bridge to one: Abilene: The Oracle campus runs on grid power with gas backup. Next door, Crusoe announced a 900 MW Microsoft campus with its own on-site plant, but the CEO of Lancium, Crusoe’s partner on the site, has described gas generation as backup. Shackelford County: Vantage is building a campus with 1.4 GW of compute for Oracle and OpenAI, designed to run off-grid on on-site gas. But its site plan includes a switchyard beside a high-voltage line — curious! Pecos County: Pacifico describes its planned microgrid (a behind-the-meter setup) at GW Ranch as never drawing from ERCOT, yet the site’s new owner, Amazon, says it’s designed to join the grid once it can connect. West Texas: Under a 20-year agreement, Chevron plans to build a dedicated gas plant beside a planned Microsoft campus that won’t initially touch the ERCOT grid, though Chevron has applied for a connection. Chevron now says the permit freeze could push its final investment decision into 2027, but it still expects first power by 2028. Armstrong County: The Google campus Crusoe is building beside a wind farm is tied to both the farm and the grid from day one, with Crusoe calling it “across the meter,” which I’ll admit is catchy. SemiAnalysis is already tracking 75 GW of equipment orders for behind-the-meter assets, but every site I’m aware of intends to connect to the grid as soon as it can, chiefly because on-site power almost always costs more. So, once the grid is available, say in year five, you switch. In the meantime, pairing on-site assets with even